Road tunnels, Boston, Massachusetts, USA

Up to 106.8m long, 24m wide, 10.8m high

 

 

Three road tunnels forming part of the new Boston Central Artery/Tunnel System have been constructed under the railway tracks leading into Boston’s South Station, which has more than 300 train movements each day.

The absolute requirement from the railway owners not to interrupt any rail services resulted in the use of jacked box tunnelling techniques.

John Ropkins Ltd in association with Edmund Nuttall Ltd provided box jacking design, planning and installation services to the Slattery / Interbeton / J.F. White / Perini joint venture through Edmund Nuttall’s sister company Interbeton Inc. It was due to Ropkins' expertise in jacked box tunnelling and Nuttall's extensive general tunnelling experience that the joint venture was able to secure a US$400m contract comprising the jacked box tunnels and associated roadworks.

Extensive ground improvement was necessary to stabilise the weak water bearing strata. Obstructions included the remains of old wharves, foundations and railway tracks, the existing sea wall and the foundation of a triple bascule rail bridge currently in use. It was decided that the only way to guarantee the integrity of the railway tracks was to freeze the ground along the alignment of each tunnel. This involved drilling a grid of vertical freeze holes to completely freeze the ground to be tunnelled through. A total of nearly 2,000 vertical freeze pipes was installed. The large size and length of these tunnels meant that they had to be split into two or three units, requiring the use of intermediate jacking stations.

The patented ‘anti-drag system’ (ADS) was used at the top and bottom of each tunnel. Using specially designed roadheaders to excavate the tunnel face, the tunnel units were jacked forward sequentially in 300mm increments. Because of limited working space, the first two units of the longest tunnel were constructed and the lead unit advanced into the ground before the third unit could be cast and the tunnelling operation completed.

The top photograph shows the lead and middle units of the longest tunnel in the jacking pit. Adjacent and to the left is a second jacking pit with a three unit tunnel under construction. Further to the left is a third jacking pit from which a two unit tunnel has been jacked into position under the railway.

An accurate vertical alignment was achieved on all three tunnels by means of a long lead unit, a carefully aligned jacking base and the bottom ADS.

This is believed to be the largest jacked box tunnelling contract ever undertaken world-wide.

This project won the British Construction Industry International Project Award 2002, and was a finalist in The Royal Academy of Engineering MacRobert Award 2002.

 

Client: Massachusetts Highways Department

System design: John Ropkins Ltd

Contractor: SIWP Joint Venture

Scope of work: Design and construct

Contract period: 48 months

Completion date: January 2001

Next - Menu - Home

© John Ropkins Ltd