Under-bridge renovations near Basingstoke, Hampshire, England

 

 

Two existing under-bridges below mainline railways were required to be strengthened and renovated whilst avoiding disruption to the train services. To achieve this, new concrete box under-bridges were constructed off line and then inserted into the voids of the existing structures.

The patented box tracking system was used to move the structures into position. This technique uses wire ropes as the slide surface and as the means of propulsion.

In each case, prior to structural work being undertaken, the existing brickwork to the bridge abutments was cleaned, repaired where necessary and repointed. One metre wide strips were excavated between the abutments and then filled with mass concrete to provide a one metre deep foundation for the tracked box in its final position.

A twelve metre long approach strip adjacent to the subway entrance was excavated and filled with hardcore. Blinding concrete was then laid on the hardcore and continued into the subway opening to provide an accurate casting base and slide path.

Groups of wire ropes were laid down along the length of the slide path and casting base.

The reinforced concrete box was then constructed, incorporating a steel soffit plate laid on top of the wire ropes and a semi-circular steel dolly built into the rear of the box base. Prior to the commencement of tracking, horizontal shear keys were cut into the existing brickwork of the abutments and the voids under the existing deck troughs filled with concrete. Steel guide angles were positioned on the slide path and the box was waterproofed.

The wire ropes were wrapped around the dolly and gripped to a steel anchor beam laid loose inside the box. Two 1300mm stroke 200t jacks provided the driving thrust, reacting against brackets fixed to the box base. The jacks pushed the anchor beam forward which pulled the ropes around the dolly, forcing the box to slide forward on the ropes.

At the end of each 1300mm stroke the jacks, anchor beam and ropes were reset and the operation repeated. It took only two hours to track the box into its final position. Gaps 50mm to 75mm wide were left around the sides and top of the box and these were later grouted.

Finally, parapets were constructed on either side of the under-bridge and the external ends faced with brickwork.

As box tracking does not require any external reaction arrangements, it is a very cost effective means of moving a box structure into position.The technique can be used for moving very much larger structures than those featured here.

 

Client: British Rail (South-West)

Designer: John Ropkins

Contractor: Edmund Nuttall Ltd

Scope of work: Design and construct

Contract period: 3 months

Completion date: March 1996

Back - Home

© John Ropkins Ltd