Lifting of 500 year old cottages. Weare Giffard, Devon, England

 

 

As part of a flood alleviation scheme on the River Torridge in north Devon for the National Rivers Authority, two sets of 500 year old stone and cob cottages were lifted by 1.5m, clear of flood water.

Yeo Cottages and Dock Cottages comprise a pair of dwellings and a terrace of six dwellings respectively. The method used for lifting the cottages was as follows.

After breaking out the existing ground floor slab, hand dug piles were installed down to bedrock at pre-determined lifting positions. A reinforced concrete column was constructed on each pile and the piles were connected by a series of reinforced concrete ground beams.

A reinforced concrete raft was cast around the columns, over the groundbeams and under the cottage walls. The raft was connected by means of high-tensile steel lifting bars to hydraulically operated jacking rigs, located on the top of the concrete columns.

The raft and cottages were then lifted up the columns in an incremental manual jacking operation.  Jack operators at each lifting position were directed via a ‘PA’ system by the lift controller. On command, each operator would pump his jack hand pump a set number of strokes.

A water level was used to check that the raft was being lifted by exactly the same amount at all jacking positions, adjustments being made as necessary. This was vital in order to avoid distortion of the raft and distress to the cottages.

Each set of cottages was lifted in increments of 3mm. After each increment, the lifting bars were supported independently of the jacks as a safeguard against hydraulic failure.

This simple manual system proved to be very effective and each set of cottages was fully lifted in less than three days without any problems.

Yeo Cottages, shown above, contain a number of Jacobean plaster details. These were protected against accidental damage and were unaffected by the lift.

On completion of jacking, permanent raft support walls were constructed on the ground beams and the jacking rigs were removed. The cottages were then refurbished and the surrounding gardens re-landscaped.

 

Client: NRA (South-West Region)

Designer: John Ropkins

Contractor: Jacked Structures Ltd

Scope of work: Design and construct

Contract period: 6 months

Completion date: December 1991