Twin cell flood relief culvert, Dorney, Berkshire, England

50m long, 27m wide, 9.5m high

 

 

A large culvert was required to be constructed through a 12m high embankment supporting a four track main line railway, to provide a vital link in a seven mile long flood alleviation channel on the River Thames, downstream from Maidenhead.

Ground conditions at the site comprised mixed clayey granular fill overlying water bearing sands and gravels overlying weathered chalk, with a water table within 1.5m of ground level.

The intended method of ensuring a stable tunnel face was to grout the embankment and use a cellular shield. However, after carrying out grouting trials it was concluded that the security of the embankment could not be guaranteed. The most certain method of stabilising the ground was to freeze it.

The normal method of freezing ground requires the installation of vertical freeze pipes. Unfortunately, this was not practicable across the railway embankment. Instead, an array of horizontal freeze pipes was installed along the culvert alignment, between the south side headwall and the north side reception pit.

Many drill steerage problems were encountered, primarily due to the granular nature of the ground and the length of the holes. A total of 180, 90mm diameter freeze and instrumentation holes were drilled. It took three months to freeze the ground, by which time a single concrete box had been constructed on a jacking base in a dewatered open-cut excavation. Freezing the sands and gravels dramatically improved their strength and stability characteristics, permitting a free-standing vertical face to be worked in an open shield.

The patented ‘anti-drag system’ (ADS) was used at the top and bottom of the box and anchored to the jacking base by means of steel tendons. To prevent the box bottom and bottom ADS from becoming frozen to the ground, heating cables were cast into the box floor.

Once the ground was frozen, the jacking pit headwall was removed and tunnelling commenced. Because the frozen sands and gravels had a strength similar to medium strength concrete it was necessary to use roadheader cutting equipment to excavate the tunnel face.

A speed restriction of 60mph was imposed on the railway during the jacking operation which took 28 days of round the clock tunnelling to complete. The maximum jacking thrust was 6,000t .

The maximum total surface settlement during jacking was 70mm. There was no movement in the direction of jacking. The culvert was installed to a horizontal alignment within 30mm of true, whilst vertical alignment was 150mm high at the front and 20mm high at the rear. The high front alignment derived from early difficulties in trimming the extremely hard frozen ground at the base of the shield, and was within the designed tolerance.

The concrete shield was used to form part of the stop log structures incorporated at each end of the box, which enable the culvert to be drained for maintenance purposes.

This was the largest box jacking project at the time, and was the first time jacked box tunnelling had been undertaken in frozen ground.

 

Client: Railtrack

System design: John Ropkins Ltd

Contractor: Edmund Nuttall Ltd

Scope of work: Design and construct

Contract period: 27 months

Completion date: December 1999

Next - Menu - Home

© John Ropkins Ltd