Twin cell rail tunnel, Lewisham railway station, London, England

48m long, 17m wide, 6.2m high

 

 

The largest of three boxes installed at Lewisham railway station, the twin cell tunnel was required to enable a new extension of the Docklands Light Railway to pass under the existing tracks and platforms.

Of particular interest on this project were the following factors. The ground through which the tunnel had to be driven was very weak comprising loose silt and sand overlying soft clay. The tunnel had to be installed at a depth of 1.7m below the rail sleepers and at a severe skew angle to the existing tracks and platforms. The tunnel passed under the existing platform foundations and through the foundations of the existing outer platform walls. Moreover, there were clear signs of past movement of the existing embankment side slope and of the platform structures on the jacking pit side. An abandoned culvert was present in the bottom right hand corner over the full length of the proposed drive.

A composite cellular shield was required to properly support the tunnel face, comprising a fabricated steel upper portion and a concrete lower portion. The steel portion could be embedded in the silts and sands whilst the relatively wide walls of the lower portion could be used to support the soft clay.

The patented ‘anti-drag system’ (ADS) was used at the top and bottom of the box and clay slurry lubricant was used at the sides.

As the jacking pit was shallow and the box very wide, anchorage for the top ADS was difficult. The ADS was anchored by a series of tendons which passed around pulleys mounted on the back of the box and which were then anchored to the jacking base. Jacks were used at the tendon anchorages to compensate for stretch in the tendons as the ADS load progressively increased to around 800t.

Differential sideways loading on the box arising from the severe skew was countered by side guides and, during the early stages of tunnelling, by the application of eccentric jacking thrust.

The tunnel was installed to within 25mm on both line and level and required a maximum jacking thrust of 4,500t. The maximum total surface settlement was 75mm and the maximum surface movement in the direction of jacking was 70mm. Track alignment was maintained by manual fettling as necessary.

Minor reinstatement work was required to the platforms after tunnelling and was carried out during routinely available night-time possessions.

The railway station and tracks remained fully operational throughout the installation period.

 

Client: Mowlem Civil Engineering Ltd

System design: John Ropkins Ltd

Contractor: Edmund Nuttall Ltd

Scope of work: Design and construct

Contract period: 14 months

Completion date: February 1998

Next - Menu - Home

© John Ropkins Ltd