Vehicular under-bridge, Silver Street station, London, England

30m long, 12.5m wide, 9.5m high

 

 

A particularly challenging project was the construction of twin box tunnels beneath Silver Street railway station, Edmonton, North London, forming part of a new vehicular underpass for the re-aligned North Circular Road.

As working space was limited, it was not possible to construct a large jacking pit capable of accommodating the boxes. Instead, a relatively small jacking pit was used and the boxes were cast at ground level as a series of counter-cast interlocking segments. These were individually lifted into the pit, mated and stressed together using longitudinal tendons. Both tunnels comprised thirty segments each weighing 160t.

Two cellular concrete shields were constructed in the jacking pit.Thrust walls were constructed at the rear of the pit and groups of jacks were arranged on jacking rigs to provide thrust at all four corners of the box. This allowed the jacking thrust to be adjusted, to provide the steerage necessary in the early stages of tunnelling when the length of box being jacked was limited.

Ground conditions at the site were very difficult. A layer of water-bearing gravel overlaid over-consolidated clay containing a layer of sand in which there was a high artesian water pressure.

To stabilise the gravel a jet grout cut-off wall was constructed around the perimeter of the proposed tunnels and the gravel inside this curtain was fully grouted. Horizontal pressure relief drains were installed to relieve the artesian water pressure in the sand layer. Horizontal ribs were incorporated in the external sides of the boxes to prevent them from becoming trapped by the over-consolidated clay as they advanced through the ground.

The north tunnel was jacked to completion first. Because the south tunnel had to pass close to a heavily loaded bridge foundation, it was jacked sideways off the north tunnel during its installation, in order to provide support to the ground underlying the bridge foundation. The patented ‘anti-drag system’ (ADS) was used at the top and bottom of both tunnels and on the side of the south tunnel adjacent to the bridge foundation.

Once the difficult operation of entering the shield through the jacking pit headwall had been achieved, each tunnel took approximately four weeks to install. The maximum jacking thrust required was 5,500t.

On completion of jacking the face was boarded, the top ADS ropes were pulled out, the longitudinal tendons were fully stressed and the perimeter voids were grouted.

In spite of the need for steerage in the early stages of tunnelling, the boxes were installed to an accuracy of 25mm on both line and level. The maximum settlement of the overlying platforms arising from the installation of both tunnels was within the 75mm maximum specified. The railway tracks carried a 20mph speed restriction and their alignment was manually adjusted on the completion of each tunnel. As the settlement curve was extremely shallow, the settlements were readily tolerated by the station structures. It was necessary, however, to re-lay the platform copings and surfacing.

 

Client: British Rail (Southeast)

Designer: John Ropkins

Contractor: Jacked Structures Ltd / J Murphy & Sons Ltd

Scope of work: Design and construct

Contract period: 18 months

Completion date: February 1995

Next - Menu - Home

© John Ropkins Ltd